Aspen SVP3 – Finished Goods Cold Warehouse

,

Our team delivered the new Finished Goods Cold Warehouse, a critical facility supporting both Work-In-Progress (WIP) and Finished Goods storage.Despite the accelerated timeline, CLS successfully completed this fast-tracked portion of the overall SVP3 facility, and the project was delivered safely, efficiently, and to the highest standards..

Project at a Glance

Timeline

  • Construction period: May – Aug 2025 (3 months)
  • Urgency: High (scope brought forward)

Facility Specifications

  • Capacity: 5 524 pallet spaces
  • Area: 2 865 m²
  • Ceiling height: 13.5 m
  • Total volume: 38 678 m³

Environmental Conditions

  • Temperature: 2 – 8 °C
  • Relative Humidity: ≤ 65%

Installed Equipment

  • Fan Coil Units: 24 (20 active + 4 redundancy)
  • Cooling Capacity: 570 kW
  • Total Airflow: 240 m³/s

Services Rendered

Facility, HVAC, Automation, Electrical, Mechanical, Validation, Process, 3d Modelling and Drafting, Civil and Structural, Contract and Financial Management, Project Management, Build Management, GMP Advisory Services.